Haveli Bahadur Shah Power Plant Conducts First Fire Test

The National Power Parks Management Company Limited (NPPMCL), GE and SEPCOIII Electric Power Construction Corporation have achieved a critical milestone in record time with the first fire of a GE 9HA gas turbine installed at the Haveli Bahadur Shah (HBS) power plant.

The project is estimated to provide to supply electricity to 2.5 million Pakistani homes. Located in the district of Jhang, about 300 kilometers from Lahore, the 1,230 megawatts (MW) project is the second of three power plants being set up in Pakistan that will run on imported supplies of liquefied natural gas (LNG).

First Fire Test Successful

First fire is a critical test where the gas turbine is switched on and run on fuel at the site. The turbine can generate up to 385 megawatts (MW) of reliable power that is expected to be distributed for residential and commercial use within a few weeks following first fire.

This significant accomplishment was achieved just 94 days after the unit was delivered to the project site. Furthermore it is the shortest duration in which a GE H-class turbine has gone from arrival at site to first fire globally. The record speed with which the project is being executed has only been possible through strong collaboration among NPPMCL, GE and SEPCOIII.

“We are taking action to provide electricity to the people of Pakistan in order to end the load shedding on an urgent basis,” said Rashid Mahmood Langrial, CEO of National Power Parks Management Company Limited (NPPMCL), the owner company of HBS power plant.

“Once complete and operating in combined cycle configuration, the Haveli Bahadur Shah power plant will help to meet up to 20 percent of the current electricity shortfall in Pakistan, providing the equivalent electricity needed to supply up to 2.5 million Pakistani homes using industry-leading technologies.”

“Our goal is to deliver cost-effective, clean and reliable power to the people of Pakistan as quickly as possible, and we are proud to have worked with our customer, NPPMCL and the government to reach this significant milestone in record time,” said Joe Mastrangelo, President and CEO of GE Power’s Gas Power Systems. “With this accomplishment, three HA turbines – our largest and most efficient gas turbine – have achieved first fire in Pakistan over three consecutive months.”

The HA is the result of almost US$2 billion in research and development and offers leading efficiency, operational flexibility and low life cycle costs. In June 2016, GE set a world record for powering the world’s most efficient combined-cycle power plant in France – EDF’s Bouchain facility – with its HA technology. Pakistan is the first country in the Middle East, North Africa, Turkey and South Asia region to use these turbines and the HBS project is expected to be even more efficient than France’s Bouchain.

The announcement of this milestone also follows the inauguration of the 1,180 MW Bhikki power plant. The project has started to generate up to 700 MW of electricity and is powered by two GE HA turbines that are currently undergoing the final stages of scheduled testing.

“We completed the Haveli Bahadur Shah project just a week after the successful inauguration of the Bhikki power plant,” said Sarim Sheikh, President & CEO of GE Pakistan, Iran and Afghanistan. “With the demand for energy rising rapidly in Pakistan, GE is proud to be part of landmark projects that will contribute towards the country’s energy security for decades to come.”

GE entered an agreement to provide two high-efficiency 9HA gas turbines, one steam turbine and two heat recovery steam generators (HRSG) to SEPCOIII, the engineering, procurement and construction (EPC) contractor for the HBS power plant in December 2015.

The project was initiated by the National Power Parks Management Company Private Limited (NPPMCL), which is solely owned by the Government of Pakistan through the Ministry of Water & Power, and was entirely funded through the Public Sector Development Programme (PSDP).


  • If I am correct this plant is the 2nd one in Pakistan to utilize the efficient GE turbine the first was Bhikki Power plant. Things seem to be moving in a positive direction.

    • That is right. Bhikki was 1170 MW.

      Should expect improvement in load-shedding in coming months provided transmission lines are already laid down. Time to start rating of electric appliances brand-wise for their power consumption and government should educate public for selection of right appliances based on these ratings. This has already started in Punjab.

  • Welldone Noon Government! Delievering all their electoral promises!

  • I am working on this project as Mechanical engineer , I will say first time in the world GE tested their turbine with over 62% efficiency , NESPAK and NPPMCL both companies had worked hard to achieve this milestone ..

  • SEPCO3 NESPAK and NPPMCL worked really hard to achieve this success.


  • Get Alerts

    Follow ProPakistani to get latest news and updates.


    ProPakistani Community

    Join the groups below to get latest news and updates.



    >