ISLAMABAD: The completion of the Sukkur-Hyderabad Motorway, the last missing link of the Karachi to Peshawar motorway network, is expected to be delayed as the successful bidder has yet to demonstrate its financial capability to undertake the project.
According to details, the bidder had quoted a bid but failed to secure sufficient pledges from local banks, despite being given six months to do so.
The details further suggest that the contractor is currently in talks with a European bank to obtain the necessary funding.
However, the Member Public Private Partnership NHA, Asim Amin, has denied that there is any delay in the execution of the project, stating that the financial matters have been settled, and land acquisition is in its final stages.
The project, which involves the construction of a 306km greenfield six-lane access-controlled motorway on a build-operate-transfer basis, has been hailed as a paradigm shift in motorway construction in the country.
Furthermore, the successful bidder, M/s Techno-CMC-ACC, offered a proposal, with a lower capital viability gap funding and no operational viability gap funding, and promised to share a higher revenue share with NHA compared to the other bidder, M/s ZKB.
Comments
Comments are closed.

Already delayed project the work is two slow damages survey completed where as Lining has since been started government claimed 5 to 6 KM lining on daily basis but it is not true lining work is slow district NF passes 64 kms so lining work requires 10 to 12 days but work surpassed the period it should be accelerated
Just wasting time and money, only chinese have the finances and resources to built such a big project.
It was supposed to be completed by now. NS approved the project then IK came he stopped the work. Then the process started in 2021 by IK govt and then it was again stopped now this new govt has started the work again and it will be delayed again definitely.
Stupidity of the state owners for delaying tactics, project was supposed deliver by 2001 which may be delayed for 100 years.
This project of sindh you should understand !