ISLAMABAD: The Interior Ministry has shared the deadline for the completion of 10th Avenue.

An amount of PKR 1,480 million has been released for the project during the last fiscal year.

The total length of 10th Avenue is 8.2-kilometer, while phase 1 will include a 5-kilometer road, starting from IJP Road to Srinagar Highway.

Furthermore, the National Logistic Cell (NLC) has been funded with an amount of PKR 10.286 billion for Phase 1 of the project.

According to the details, the construction work was started in March and is expected to complete within 21 months.

The project was expected to be completed within 21 months. However, as per the details on the NLC’s official site, the project is expected to be completed in September 2023.