Another Rs. 3.45 Billion Flyover Announced for Rawalpindi

Work on Rawalpindi’s Rs. 35.28 billion infrastructure overhaul has accelerated, with major flyovers and underpasses moving toward completion under Punjab government funding.

The project spans both city and cantonment areas and includes four flyovers and eight underpasses. Officials have now approved an additional flyover at Ammar Shaheed Chowk, following a surge in traffic at the interchange.

The new structure is estimated to cost Rs. 3.45 billion, and construction will begin next year once the case receives final clearance.

Ad Powered By Advergic
Loading ad . . .
Ad - Continue scrolling to read

So far, authorities have completed one flyover and two underpasses, while work continues on two flyovers and three underpasses. Construction on three more underpasses will begin on December 20.

The Nawaz Sharif Flyover at Khawaja Corporation Chowk, built for Rs. 4.4 billion, is already open to traffic, and Adiala Road remains under redesign and expansion. The GPO Chowk and TMA Chowk underpasses, completed at a cost of Rs. 5.7349 billion, are also operational.

At Kachehry Chowk, work on a flyover and underpass launched on November 3 for Rs. 5.974249 billion is expected to finish by April 30, 2026. The linked Jinnah Park flyover and underpass, costing Rs. 4.672245 billion, are scheduled for completion by March 30, 2026.

Another major ongoing project is the underpass and road expansion on Iftikhar Janjua Road, worth Rs. 2.688073 billion, which is expected to finish by January 30, 2026.

Stay Connected with ProPakistani

Get the latest automobile news, car launches, bike reviews, videos and analysis wherever you prefer.

Add ProPakistani to Preferred Sources and see more of our stories in Google Search and Top Stories.

Share
Published by
Arsalan Khattak