Major Progress Made on Rs. 14 Billion Road Project in Rawalpindi

Commissioner Rawalpindi Division Engineer Amir Khattak reviewed progress on the Kutchery Chowk remodeling and construction project and received a detailed briefing from project officials. They reported that crews have completed 42 percent of the overall work so far.

Officials said workers have finished guide beam construction at the Iftikhar Janjua Underpass. Teams have also completed guide beam and piling work at Kutchery Chowk and the Jinnah Park Underpass.

In addition, crews have completed 90 percent of the retaining wall, while construction of the boundary wall continues at full pace. Officials confirmed that the work is moving according to the approved schedule and will reach completion in May this year.

Commissioner Khattak expressed satisfaction with the progress and directed departments to maintain the current pace to meet the deadline. He instructed officials to ensure strict adherence to approved engineering standards and emphasized that the administration will not compromise on construction quality.

The commissioner also directed departments to strengthen traffic management and public facilitation measures during construction to minimize inconvenience to residents.

He further ordered officers to enhance monitoring, maintain transparency, and improve coordination among departments to ensure timely and successful completion of the project.

Stay Connected with ProPakistani

Get the latest automobile news, car launches, bike reviews, videos and analysis wherever you prefer.

Add ProPakistani to Preferred Sources and see more of our stories in Google Search and Top Stories.


  • Excellent job done so far, hope target will be achieved within time frame, finance and quality work.

  • There are No Rules of Driving/Riding and U-turns are not protected, means infrastructure is useless without Implementing Rules.

  • Sir Asslam u alaikum great project for the Rawalpindi and other cities especially for patients and the students. I want to draw a intention on pearl continental chowk at Mall Rd. There must b a under pass (I was afraid how such a crucial point was missed by authorities in last project) almost divert 20% of the traffic 🚦 free towards CMH GHQ, and Adaylia Rd ….. etc automatically diverted.
    Regards

  • Due to construction of under pass at Khuchery Chowk traffic has been diverted towards other arteries in the area. It is requested to have easy unrestricted traffic flow all encroachments hindering the flow of traffic be removed immediately.


  • Get Alerts

    ProPakistani Community

    Join the groups below to get latest news and updates.



    >